Freeport LNG provides update on restart of liquefaction facility
https://www.lngindustry.com/liquefaction/03012023/freeport-lng-provides-update-on-restart-of-liquefaction-facility/
PL704, restart in Feb 2023.?

Published by?Jessica Casey,?Deputy Editor
LNG Industry,?Tuesday, 03 January 2023 14:00
Freeport LNG has provided an update on the timing of the initial restart of its liquefaction facility. The company continues to make notable progress on its path towards the restart of liquefaction operations. As of 23 December 2022, the reconstruction work necessary to commence initial operations is substantially complete, and the company is submitting responses to the last remaining questions included in the Federal Energy Regulatory Commission's December 12 data request.
Given the time needed for the regulatory agencies to review the company's responses and to seek any necessary clarification, Freeport LNG now does not anticipate commencing the initial restart of its liquefaction facility until the second half of January 2023.
The company continues to have close, collaborative engagement with the regulatory agencies and that engagement will continue as Freeport LNG works towards the safe restart of its facility.

Restart of Freeport LNG’s Texas facility on hold until late January 2023
https://www.offshore-energy.biz/restart-of-freeport-lngs-texas-facility-on-hold-until-late-january-2023/
December 26, 2022, by?
US liquefied natural gas (LNG) export company Freeport LNG has updated the timing of the initial restart of its liquefaction facility in Texas which has been shut since June.
To remind, the facility has been shut down following the?explosion incident?that occurred on 8 June. At first, the restart of initial operations was targeted for?early October, which was then?pushed back to mid-November.
On 14 November, the operator announced that the reconstruction work was approximately 90% complete, targeting initial production at the facility in mid-December.

However, in its latest update, Freeport LNG once again delayed the restart of its liquefaction facility.
“As of?23 December, the reconstruction work necessary to commence initial operations is substantially complete, and the company is submitting responses to the last remaining questions included in the Federal Energy Regulatory Commission’s?12 December?data request”, Freeport LNG said in a statement.
“Given the time needed for the regulatory agencies to review the company’s responses and to seek any necessary clarification, Freeport LNG now does not anticipate commencing the initial restart of its liquefaction facility until the second half of?January 2023.”